We can promise 365 days free updates
In order to meet the needs of all customers that pass their exam and get related certification, the experts of our company have designed the updating system for all customers. Our CCM exam question will be constantly updated every day. The IT experts of our company will be responsible for checking whether our CCM exam prep is updated or not. Once our CCM test questions are updated, our system will send the message to our customers immediately. If you use our CCM exam prep, you will have the opportunity to enjoy our updating system. You will get the newest information about your exam in the shortest time. You do not need to worry about that you will miss the important information, more importantly, the updating system is free for you, so hurry to buy our CCM exam question, you will find it is a best choice for you.
Printable format of the PDF version
Maybe most of people prefer to use the computer when they are study, but we have to admit that many people want to learn buy the paper, because they think that studying on the computer too much does harm to their eyes. CCM test questions have the function of supporting printing in order to meet the need of customers. You can print our CCM exam question on papers after you have downloaded it successfully. It not only can help you protect your eyes, but also it will be very convenient for you to make notes. We believe that you will like our CCM exam prep.
According to the market research, we have found that a lot of people preparing for the CCM exam want to gain the newest information about the exam. In order to meet all candidates requirement, we compiled such high quality study materials to help you. It is believed that our products will be very convenient for you, and you will not find the better study materials than our CCM exam question. If you willing spend few hours to learn our study materials, you will pass the exam in a short time. Now we are going to introduce our CCM test questions to you.
We provide practice offline in anytime
People are very busy nowadays, so they want to make good use of their lunch time for preparing for their CCM exam. As is known to us, if there are many people who are plugged into the internet, it will lead to unstable state of the whole network, and you will not use your study materials in your lunch time. If you choice our CCM exam question as your study tool, you will not meet the problem. Because the app of our CCM exam prep supports practice offline in anytime. If you buy our products, you can also continue your study when you are in an offline state. You will not be affected by the unable state of the whole network. You can choose to use our CCM exam prep in anytime and anywhere.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. (Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)? Choose all correct answers.)
A) The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that a Variation shall be executed on a daywork basis.
B) If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.
C) The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.
D) The dayworks related Sub-Clause is also applicable to other types of works.
2. (Under the FIDIC Yellow Book (edition 1999), any delay caused by Authorities will be considered as a cause of Delay under sub paragraph (b) of Sub-Clause 8.5 under the only condition that the Contractor has diligently followed the procedures laid down by the public authorities in the Country. Is this statement true or false?)
A) False
B) True
3. (You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
A) Both Parties should be present at the meeting in which the DAAB provides assistance.
B) The Employer and the Contractor have identified an issue and disagreement, and have agreed between themselves that they want the DAAB to provide assistance and/or informally discuss and attempt to resolve that issue/disagreement.
C) The Engineer has made a non-objection letter, in which it is stated that the issue/disagreement does not concern the matter that is being dealt with by the Engineer.
D) The Employer and the Contractor have made a " joint request " in writing before the DAAB gives the requested assistance.
4. Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?
A) The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.
B) The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).
C) Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.
5. What does discharge confirm under the FIDIC Red Book (edition 1999)?
A) It confirms full and final settlement of all money due to the Contractor.
B) It confirms the immediate end to the Contract unconditionally whenever issued.
C) None of the above three statements is correct.
D) It confirms interim settlement of all money due to the Contractor
Solutions:
| Question # 1 Answer: A,B | Question # 2 Answer: B | Question # 3 Answer: C | Question # 4 Answer: A | Question # 5 Answer: A |