NEW QUESTION # 57
One purpose of risk management is to:

  • A. manage variations in a controlled way
  • B. adapt the plan to resolve problems.
  • C. continually improve the project teams' efficiency.
  • D. minimise threats and maximise opportunities.

Answer: B


NEW QUESTION # 58
The document that identifies what information needs to be shared, to whom, why, when and how is called the:

  • A. stakeholder mapping grid.
  • B. document distribution schedule.
  • C. communication management plan.
  • D. responsibility assignment matrix.

Answer: C


NEW QUESTION # 59
The main purpose of configuration management is to:

  • A. provide control of the deliverables and avoid mistakes or misunderstandings.
  • B. ensure that the final product meets the strategic needs of the business.
  • C. minimise the impact of changes on the scope of the project.
  • D. maximise the impact of agreed enhancements on the project deliverables.

Answer: A


NEW QUESTION # 60
What is a key role of the project manager?

  • A. Coordinating the development of the project management plan.
  • B. Conducting benefits realisation reviews.
  • C. Reviewing progress against success criteria and checking that the planned business benefits will be achieved.

Answer: A

Explanation:
D Authorising any changes to the business case.


NEW QUESTION # 61
What is a factor that is important when communicating as part of stakeholder engagement?

  • A. Planned communication will reduce the power of stakeholders who are likely to have an interest in the project.
  • B. Planned communication is likely to reduce the number Of valid stakeholders who have an interest in the project.
  • C. Planned communication will help to establish the level of interest and power a stakeholder is likely to possess.
  • D. Planned communication will increase the number of stakeholders who are likely to have an interest in the project.

Answer: C


NEW QUESTION # 62
Which of the following best describes a project environment?

  • A. The structured method used to control the project.
  • B. The type of organisation concerned with implementation.
  • C. The context within which a project is undertaken.
  • D. An understanding of the risks involved in the project.

Answer: C


NEW QUESTION # 63
Which one of the following is NOT a function of leadership?

  • A. Inspiring the individual.
  • B. Maintaining constant tight control.
  • C. Promoting the project vision.
  • D. Reinforcing positive relationships.

Answer: B


NEW QUESTION # 64
What is the main reason for an initial high-level review of a change request?

  • A. To implement the necessary actions to ensure the change has a smooth implementation.
  • B. To consider if the change is feasible to evaluate at this stage.
  • C. To establish who might be the best stakeholders to be involved in the change.
  • D. To ensure that the change request is considered as soon as possible.

Answer: B


NEW QUESTION # 65
Which one of the following is a generic project management process?

  • A. Learning and closing.
  • B. Risk management.
  • C. Quality management.
  • D. Staff appraisal.

Answer: A


NEW QUESTION # 66
What is an example of a project management office activity that would be most likely undertaken to support a project?

  • A. Carrying out A. health check.
  • B. Developing the business case.
  • C. Developing the project management plan.

Answer: A

Explanation:
D Carrying out day-to-day resource management.


NEW QUESTION # 67
Establishing success criteria is important at the start of the project, as they:

  • A. ensure comprehensive risk analysis.
  • B. ensure adequate resource allocation.
  • C. indicate how the stakeholder needs will be met.
  • D. indicate what is important in supplier selection.

Answer: C


NEW QUESTION # 68
Which of these is a correct definition of an Estimate?

  • A. An estimate is an approximation of project time and cost targets that forms the basis of the contract
  • B. An educated guess that improves over time
  • C. The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work
  • D. A forecast of the probable time or cost of completing work

Answer: D


NEW QUESTION # 69
Who owns the Project Management Plan (PMP)?

  • A. The chief executive.
  • B. The project support office
  • C. The project manager.
  • D. The project team.

Answer: A


NEW QUESTION # 70
What is the purpose of a stakeholder grid?

  • A. A means of stakeholder identification.
  • B. It provides a statement of the stakeholder communications plan.
  • C. It presents an action plan for stakeholder management.
  • D. To understand a stakeholder's position in relation to the project.

Answer: D


NEW QUESTION # 71
Within which phases of a project life cycle are risks identified?

  • A. Within each phase.
  • B. Within the initial phases.
  • C. Within the end phase.
  • D. Within the deployment phase.

Answer: A


NEW QUESTION # 72
A key output of a well-controlled configuration management process is:

  • A. documented evidence of all project changes: proposed. authorised, rejected or deferred.
  • B. documented traceability between versions of each configuration item.
  • C. an agreed point after which no further changes to scope will be considered.
  • D. that the project is most likely to meet its success criteria.

Answer: B


NEW QUESTION # 73
Which of the following is an activity in a typical risk management process?

  • A. Closure.
  • B. Request.
  • C. Verification.
  • D. Justification

Answer: A


NEW QUESTION # 74
Which one of the following is NOT a project change?

  • A. A. requirement for extra expenditure to cover increased supplier costs.
  • B. An approved omission from the agreed project scope.
  • C. The removal of work packages from the agreed project scope.
  • D. The potential for agreed resources to be removed from the project.

Answer: D


NEW QUESTION # 75
Which one of these categories would best represent project issues?

  • A. Threats to the project which cannot be resolved by the project manager.
  • B. Opportunities that occur through change control.
  • C. Problems that the project manager has to deal with on a day-to-day basis.
  • D. Uncertain events that may or may not occur.

Answer: A


NEW QUESTION # 76
Once a change has been requested what is the next step in the change control process?

  • A. Advise the sponsor.
  • B. Evaluate the change.
  • C. Update the change log.
  • D. Update the project plan.

Answer: B


NEW QUESTION # 77
Who in the project is responsible for benefits realisation?

  • A. The sponsor.
  • B. The project manager.
  • C. The senior management of the organisation.

Answer: A

Explanation:
D The end users.


NEW QUESTION # 78
Which of the following are not considered by quality planning?

  • A. Staff qualified to undertake inspections.
  • B. Contingency budget for remedial work.
  • C. Processes to obtain stakeholder approvals.
  • D. Equipment required for quality testing.

Answer: B


NEW QUESTION # 79
Scheduling can best be defined as the process used to determine:

  • A. project cost.
  • B. overall project duration.
  • C. sub-contractor's responsibilities
  • D. the project management plan.

Answer: B


NEW QUESTION # 80
......

Ace APM APM-PFQ Certification with Actual Questions Oct 14, 2025 Updated: https://www.updatedumps.com/APM/APM-PFQ-updated-exam-dumps.html

2025 The Most Effective APM-PFQ with 408 Questions Answers: https://drive.google.com/open?id=1sCT4poG6hmZvuGTztYFdJWD_kOoWGg2_